DOWNTOWN IMPROVEMENT (PHASE 2)
NEIGHBORHOOD NOTICE
The sidewalk and street work for the downtown improvements is scheduled to begin Monday May 21st, 2012, with excavation starting on Wednesday May 23rd. We would like to remind you that all personal items on the City sidewalks must be removed prior to sidewalk excavation of your section and remain off until further notice. Items left on in city right-of-way may be disposed of by the contractor at his discretion to allow the construction work to proceed. The work will progress as previously discussed in the Neighborhood meetings. The following is a tentative schedule (subject to change) for the blocks affected:
West Side of Trade (6th to 5th Street)
Sidewalk Excavation May 21st thru June 14th
Sidewalk Concrete Pour on June 12th, 13th or 14th (We will follow-up with exact date later)
West side of Trade (5th to 4th Street)
Sidewalk Excavation June 11th thru June 28th
Sidewalk Concrete Pour on June 25th, 26th or 27th (We will follow-up with exact date later)
East Side of Trade St. (Sherman to Maddox)
Sidewalk Excavation June 25th thru August 6th
Sidewalk Concrete Pour on July 18th, 19th, 23rd, Aug 1st or 2nd (We will follow-up with exact date later)
Night-time Paving
August 7th thru August 10th
Remember access will be restricted to pedestrians only (No Vehicle access from Trade Street) during construction and no access from Trade Street will be available during sidewalk pours. We will continue to provide updates as the project progresses. If you have any questions please feel free to contact Charles Eaton at 503-884-6236.